The Complete Guide To Mivan Construction Technology

Real estate developers are employing Mivan Technology, a cutting-edge technology that simultaneously ensures the structure’s endurance and lowers building costs without sacrificing quality. The nation’s housing shortage can be eliminated with the help of Mivan technology.


Are you searching for new projects in virar?


 

Did you realise that traditional construction methods can be replaced by mivan shuttering? Although most Indian real estate developers and homebuyers may be wary about mivan technology, the Indian real estate industry needs to give mivan construction a try if issues like project delays and a shortage of trained labour are to be resolved. Let’s examine what “mivan formwork” actually implies and how it benefits the real estate industry.

 

Mivan Shuttering: What Is It?

Mivan shuttering, a type of aluminium formwork, has spread throughout the world and shown to be a cost-effective replacement for the labour- and time-intensive traditional technique of construction. Construction with Mivan technology is cost-effective when it is a huge construction. Bricks are not use at all in Mivan technology, and all the components—beams, walls, slabs, staircases, etc.—are form of concrete. Similar to how modular kitchens have taken the place of traditional ones, improving space efficiency, aesthetic appeal, and building speed, mivan technology formwork has benefited the real estate industry. Without taxes, the shuttering cost in Mivan ranges from Rs 8,000 to Rs 9,000 per sqm.

 

What is the definition of formwork?

It is a temporary structure that offers support for new concrete until it can stand on its own. In a tall tower project, the type of formwork used impacts the price, quality, and speed of construction. Formwork is made of a variety of materials, including aluminium, plastic, steel rebar, and wood. One of the most recent advancements in formwork technology that is appropriate for the Indian building industry is mivan shuttering.

 

How does the Mivan shuttering process work?

Mivan formwork is very similar to other formwork in terms of its practices and procedures. The steel used for wall reinforcement is initially utilise to form the construction. The pre-cast steel is shipped from the mill to the construction site. Simply put, it is created to order. Mivan building uses only materials that are specifically sized to fit the specifications of the home structure, whether they be slabs or beams. Mivan shuttering can be disassembled after being assembled. The formwork for the Mivan construction has been set up so far; the next phase is to pour concrete over it to reinforce the shape. The formwork is then remove after a predetermine amount of time has passed during which the Mivan building structure gains the necessary strength.

 

‘Housing for All by 2024’ used the Mivan shuttering

Mivan shuttering is widely utilised throughout the world, notably in Asia, Europe, and the Middle East, for construction-related uses. The most ambitious project of the Indian government, “Housing for All by 2024,” makes considerable use of Mivan shuttering.

 

Benefits of shuttering Mivan

  • Construction projects can be completed more quickly and occasionally with higher quality thanks to mivan technology.
  • When Mivan technology is applied, the finishing is smooth. There is an economy of scale and it is not labor-intensive.
  • Construction forms made by Mivan can be recycled up to 250 times.
  • Because Mivan structure is compose of concrete, neither builders nor homeowners need to spend much on maintenance.
  • Assist in the building of thinner walls to enable larger carpet areas.
  • Higher resistance to earthquakes.

 

What disadvantages does conventional formwork have?

  • The cost of traditional formwork is high.
  • Takes more time to finish.
  • Use of this requires skilled labour.
  • high expense of maintenance.
  • After installation, must be plastered, making disassembling difficult.
  • The carpet area is decreased due to the construction of thicker walls.
  • The formwork needs to be installs and remove with a lot of manpower.
  • It can only be use 10 times in total.
  • If there is a seismic disturbance, its structural integrity is compromised.

 

Disadvantages of Mivan construction

  • For modest projects, aluminium formwork could not be cost-effective due to its high cost.
  • Only if you see mivan construction on a large scale is it advantageous.
  • These oughts to have consistent layouts as well.
  • Although the procedure doesn’t require a lot of labour, a professional crew is essential to ensuring that tasks like alignment and concrete pouring are completed on schedule and with expertise.

 

Shuttering formwork components, Mivan

There are four different categories for the Mivan shuttering formwork:

  • Wall panels, stub pins, kickers and rockers are among the wall component shuttering formwork used by Mivan.
  • Soffit length, deck panels, and deck prop & prop length are among the deck component shuttering formwork used by Mivan.
  • The beam side panel, prop head, and panel for soffit beam are all parts of the Mivan shuttering formwork for beam components.
  • Aside from the aforemention three components, the Mivan shuttering formwork is use for other components.

 

Construction using Mivan shutters as opposed to traditional formwork

Parameter Mivan shuttering construction system Regular formwork
Accuracy in construction Accurate Accuracy lesser than modern systems
Speed of development 7 days/floor Minimum 21 days/floor
Seismic resistance Good resistance Comparatively lesser
Type of construction Cast-in-situ cellular construction Simple RCC
Dismantling floor piece frames without expelling props Possible Impossible
Quality of surface finish Excellent Putting is requires
Coordination between offices Essential Not required
Wastage Very little Comparatively higher
Pre-planning of formwork system Required Not required

 

 

Video Source

 


You’re looking for Projects in Mulund we have the Best Properties In Mumbai Like Ready to Move:https://navimumbaihouses.com/properties/search/mulund/

If you want daily property update details please follow us on Facebook Page / YouTube Channel / Twitter

Disclaimer: The views of this expressed above are for informational purposes only based on the industry reports & related news stories. Navimumbaihouses.com does not guarantee the accuracy of this article, completeness, or reliability of the information & shall not be held responsible for any action taken based on the published information.
Back to top
Also Read

Buy Properties in Bandra